BP WEST COAST PRODUCTS L.L.C.

hazardous_liquid Incident — — December 28, 2010

Incident Information

Incident DateDecember 28, 2010
OperatorBP WEST COAST PRODUCTS L.L.C.
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates33.86333, -118.16389

Cause

CauseCORROSION FAILURE
SubcauseINTERNAL CORROSION

Casualties

Fatalities0
Injuries0

Costs

Property Damage$123,000
Emergency Response$33,000
Other Costs$0

Location Map

Incident Narrative

"DEC 28, 2010 @ APPROXIMATELY 19:05 HOURS, BP WEST COAST LAS BASIN CONTROL CENTER (OCC) WAS NOTIFIED OF A RELEASE BETWEEN PLAINS ALL AMERICA (PAAP) TANKS 603 & 607, A CRUDE OIL RELEASE AT 5900 CHERRY AVENUE, PLAINS ALL AMERICA FACILITY. PLAINS ALL AMERICAN IDENTIFIED TO BP WEST COAST OPERATIONS OF A CRUDE OIL LEAK ON PLAINS PROPERTY AFTER THEY BEGAN RESPONSE TO CRUDE. PLAINS ASSUMED LEAK WAS THEIR FACILITY PIPELINE. BP OCC MADE INTERNAL NOTIFICATIONS & DISPATCHED PERSONNEL TO SITE. PAAP BEGAN EXCAVATION& CLEAN UP ACTIVITIES. AT APPROXIMATELY 21:22, PAAP NOTIFIED BP OCC SPILL WAS FROM 20"" PAAP PIPELINE. BP PERSONNEL RELEASED FROM SITE. AT APPROXIMATELY 23:45, PAAP NOTIFIED BP OCC RELEASE WAS NOT EMINATING FROM PAAP AS ORIGINALLY THOUGHT. BP OCC MADE INTERNAL NOTIFICATIONS AND DISPATCHED PERSONNEL TO SITE @ 00:18 HOURS 12/29/2010. BP PERSONNEL ONSITE AFFIRMED RELEASE FROM BP 16"" FILL LINE TO TANK 603. LINE WAS DRAINED DOWN & SECURED. TANKS 601, 602, 603, 605, & 606 SHARE A COMMON FILL LINE FROM THE PIPELINE. FOUND TANKS 601, 602, & 603 FILL LINES ARE BLINDED OFF. THERE HAVE BEEN NO RECORDED DELIVERIES INTO TANK 603 FROM 2000 TO 2011, AS TANKS 605 & 606 ARE ROUTINE DELIVERIES. HOWEVER, FLOW INTO THESE TANKS DO NOT SUFFICIENTLY FLUSH THE FILL LINE TO TANK 603. BP WAS NOT THE OWNER/OPERATOR OF THE FACILITY AT THE TIME WEST HYNES TERMINAL WAS SOLD IN 2000 TO PACIFIC PIPELINE. IT IS UNKNOWN WHY FILL LINES TO TANK 601, 602, & 603 NOT PURGED. THE BP 16"" FACILITY LINE TRANSFERS CRUDE TO TANKS FROM EAST HYNES TO WEST HYNES. IT IS CONNECTED TO EAST HYNES VIA THE IVEC LINE (CSFM # 0976). THE CAUSE WAS DEEMED TO HAVE BEEN CORROSION. THE CSFM'S MR. WILLIAMS IS IN COMMUNICATION W/ BP FOR FOLLOW QUESTIONS FOR THIS INCIDENT ALSO. BP WITH CSFM DISCUSSED THE LINE IS INTRA FACILITY (PLANT, LOW STRESS) NON PIGGABLE."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in