COLONIAL PIPELINE CO

hazardous_liquid Incident —

Incident Information

Report Date
OperatorCOLONIAL PIPELINE CO
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates37.15778, -78.83500

Cause

CauseNATURAL FORCE DAMAGE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON MARCH 31, 2010, A CRACKED TEE FITTING CONNECTING THE LEAK DETECTION TUBING TO A 2 INCH DRAIN LINE WAS DISCOVERED. THE FITTING WAS IMMEDIATELY REPLACED, ELIMINATING THE SOURCE, AND VADEQ WAS NOTIFIED OF THE CONFIRMED RELEASE. ADDITIONAL DIGGING WAS CONDUCTED TO REMOVE SOILS THAT WERE CONTAMINATED. SOILS, WATER AND OIL REMOVED WERE ALL SHIPPED OFF-SITE FOR PROPER TREATMENT AND RECYCLING. SAMPLING TO VERIFY CONTAMINANT REMOVAL WAS CONDUCTED ON APRIL 14, 2010. ON 4-30-2010 TOTAL COST WERE ESTIMATED TO BE $56,170. ACCORDINGLY, A TELEPHONIC NOTICE WAS MADE TO THE NATIONAL RESPONSE CENTER. THE CRACKED TEE FITTING WAS ANALYZED BY A THIRD-PARTY METALLURGIST AND IT IS BELIEVED THAT WATER/MOISTURE FROZE INSIDE THE FITTING RESULTING IN A CRACKED FITTING.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.