SUNOCO PIPELINE L.P.

hazardous_liquid Incident —

Incident Information

Report Date
OperatorSUNOCO PIPELINE L.P.
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates36.41936, -97.84852

Cause

CauseINCORRECT OPERATION
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ENID STATION WAS SHUT DOWN TO ADD A NEW RELIEF SYSTEM. GAUGER TURNED THE VALVE TO THE OPEN POSITION BUT WASN'T COMPLETELY SURE OF THE POSITION. HE DID NOT TRY TO CLOSE THE VALVE TO VERIFY THE POSITION PRIOR TO STARTUP. ON STARTUP , THE GAUGER FOUND THE TWO BACK PRESSURE VALVES HAD FAILED. APPROXIMATELY 20 GALLONS OF CRUDE SPRAYED ON THE GRAVEL. GAUGER NOTIFIED CONTROL CENTER TO SHUT LINE DOWN. NO OVER PRESSURE OF THE LINE OCCURRED. RE-SUBMITTED ON 3/26/2013 TO INCLUDE PART E5F PER PHMSA REQUEST.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.