BELLE FOURCHE PIPELINE CO

hazardous_liquid Incident — — November 13, 2011

Incident Information

Incident DateNovember 13, 2011
OperatorBELLE FOURCHE PIPELINE CO
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates46.86168, -102.77762

Cause

CauseEXCAVATION DAMAGE
SubcauseEXCAVATION DAMAGE BY THIRD PARTY

Casualties

Fatalities0
Injuries0

Costs

Property Damage$29,525
Emergency Response$2,835
Other Costs$0

Location Map

Incident Narrative

CONTRACTOR INSTALLING WATER AND SEWER LINES TO KLD TRUCKING FACILITY STRUCK MARKED GATHERING LINE COMPROMISING IT AND SPILLING CRUDE INTO THE BELL HOLE/DITCH IN WHICH THE CONTRACTOR WAS WORKING. CONTRACTOR ORIGINALLY CALLED ONE-CALL ON 10/14 AND BELLE FOURCHE PIPELINE LOCATED WITH PIN FLAGS THE LOCATION OF THE FACILITY. BELLE FOURCHE ASKED TO BE ON SITE DURING EXCAVATION AND ASKED ON MULTIPLE OCCASIONS FOR A MEET TIME. CONTRACTOR DID NOT RESPOND AND DID NOT BEGIN DIGGING UNTIL AFTER THE INITIAL LOCATE REQUEST HAD EXPIRED. ON SUNDAY NOVEMBER 13TH, WHILE DIGGING TO INSTALL SEWER LINES, CONTRACTOR COMPROMISED THE BELLE FOURCHE OIL GATHERING PIPELINE SPILLING ABOUT 200 BARRELS OF CRUDE INTO DITCH AND CONTAMINATING SURROUNDING SOILS. AN UPDATE EXCAVATION NOTICE WAS NOT EXECUTED UNTIL NOVEMBER 16TH (TICKET #11155260). STRIKE OCCURED AT APPROXIMATELY 8:00 A.M. ON NOVEMBER 13TH AND BELLE FOURCHE HAD EMPLOYEES ON THE SCENE AROUND 8:45. LINE WAS SHUT DOWN AND REPAIRED BY CUTTING OUT A SEGMENT AND WELDING IN NEW PIPE. ON NOVEMBER 14TH AT APPROXIMATELY 4:00 P.M. BELLE FOURCHE RESTARTED THE PIPELINE.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in