KINDER MORGAN CO2 CO. LP

hazardous_liquid Incident — — April 3, 2012

Incident Information

Incident DateApril 3, 2012
OperatorKINDER MORGAN CO2 CO. LP
CommodityCO2 (CARBON DIOXIDE)
Pipeline Typehazardous_liquid

Location

State
Coordinates33.03138, -102.82027

Cause

CauseINCORRECT OPERATION
SubcauseWRONG EQUIPMENT SPECIFIED OR INSTALLED

Casualties

Fatalities0
Injuries0

Costs

Property Damage$2,911
Emergency Response$0
Other Costs$0

Location Map

Incident Narrative

THERMAL RELIEF VALVE AT SHEEP MOUNTAIN STATION PREMATURELY RELIEVED ON APRIL 3, 2012. RELIEF VALVE WAS SET AT 2,625 PSIG. PUMP STATION WAS OPERATING AT 2,175 PSIG. RELIEF VALVE WAS SPECIFIED WITH INCORRECT SEAT MATERIAL DURING PRE-CONSTRUCTION PHASE. AS A RESULT OF OUR INVESTIGATIONS, WE CHECKED THE MATERIAL SPECIFICATIONS FOR THE REMAINING NEWLY INSTALLED VALVES (7). WE FOUND THAT ALL 7 ALSO HAD INCORRECT SEAT MATERIAL, AND REPLACED EACH ONE.