KOCH PIPELINE COMPANY, L.P.

hazardous_liquid Incident — — August 9, 2012

Incident Information

Incident DateAugust 9, 2012
OperatorKOCH PIPELINE COMPANY, L.P.
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates27.82692, -97.19857

Cause

CauseINCORRECT OPERATION
SubcauseTANK, VESSEL, OR SUMP/SEPARATOR ALLOWED OR CAUSED TO OVERFILL OR OVERFLOW

Casualties

Fatalities0
Injuries0

Costs

Property Damage$937
Emergency Response$82,641
Other Costs$0

Location Map

Incident Narrative

ON AUGUST 9, 2012 AT 13:28 THE PIPELINE CONTROL CENTER RECEIVED A SUMP ALARM ON THE INGLESIDE TO VIOLA 16"" AT INGLESIDE PUMP STATION & BEGAN SHUTTING THE LINE DOWN. KPL OPERATION TECHNICIANS WERE ONSITE, PERFORMING ROUTINE MAINTENANCE, WHEN THE RELEASE OCCURRED. APPROXIMATELY 3 BBLS OF PRODUCT WAS RECOVERED BY USING THE VACUUM TRUCK, ALREADY ONSITE FOR THE MAINTENANCE ACTIVITY. KPL PERSONNEL MADE INTERNAL NOTIFICATIONS AT 13:49, AS WELL AS REQUESTED OSRO DEPLOYMENT. INITIAL INVESTIGATION REVEALED THAT THE 2"" SUMP DRAIN LINE BALL VALVE, LEFT EITHER FULL OR PARTIALLY OPEN, CONTRIBUTED TO THE OVERFILL OF THE SUMP. CLEANUP WAS COMPLETE ON AUGUST 10, 2012.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in