PHILLIPS 66 PIPELINE LLC

hazardous_liquid Incident —

Incident Information

Report Date
OperatorPHILLIPS 66 PIPELINE LLC
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates35.26528, -101.89083

Cause

CauseINCORRECT OPERATION
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

A 2 INCH VALVE (OFF THE 8-INCH AMARILLO TERMINAL TO SAAL PIPELINE TRANSFER LINE TO 3RD PARTY) WAS RECENTLY INSTALLED AS PART OF A PROJECT AT THE AMARILLO TERMINAL. THE VALVE WAS LOCKED, PLUGGED, AND PRESSURE TESTED AFTER INSTALLATION. SUBSEQUENT TO INITIAL INSTALLATION, A CONTRACTOR EMPLOYEE REMOVED THE PLUG IN THE VALVE (WITHOUT PROPER AUTHORIZIATION OR KNOWLEDGE OF THE OPERATOR) AND FAILED TO PROPERLY RE-INSTALL THE PLUG. THE CONTRACTOR EMPLOYEES WHO REMOVED THE PLUG IN THE VALVE WERE NOT OQ QUALIFED TO PERFORM THIS TASK WITHOUT SUPERVISION. BECAUSE THE PLUG WAS NOT PROPERLY REINSTALLED AFTER THE UNAUTHORIZED REMOVAL, THE PLUG LEAKED REFINED PRODUCT AROUND THE THREADS OF THE PLUG AFTER THE LINE WAS STARTED. THE PLUG LEAKED FOR APPROXIMATELY 52 HOURS (OVER THE WEEKEND) BEFORE DISCOVERY DUE TO THE FACT THAT THE TERMINAL IS NOT MANNED 24/7. NO D&A TESTING WAS PERFORMED BECAUSE DISCOVERY OCCURRED 52 HOURS AFTER THE EVENTS WHICH COULD HAVE CAUSED THE LEAK.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in