BUCKEYE PARTNERS, LP

hazardous_liquid Incident —

Incident Information

Report Date
OperatorBUCKEYE PARTNERS, LP
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates43.51946, -83.81743

Cause

CauseNATURAL FORCE DAMAGE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON FEBRUARY 9, 2014 AT APPROXIMATELY 05:25 THE BUCKEYE CONTROL CENTER INDICATED THAT THE PRESSURE WAS DECREASING ON THE WF208WB LINE. THE LINE WAS SHUT DOWN PER NORMAL OPERATING SCHEDULES. THE INITIAL PRESSURE ON THE LINE WAS 276 PSI. IT WAS DISCOVERED THAT AN ANCILLARY 3/4"" LINE LEADING TO THE GRAVITOMETER HAD BUCKLED DUE TO COLD WEATHER RESULTING IN A CRACK WHICH CAUSED THE RELEASE. BOTH THE SUCTION LINE AND THE RETURN LINE OF THE GRAVITOMETER WERE REPLACED AND THE LINE RETURNED TO SERVICE FOR NORMAL OPERATIONS ON FEBRUARY 12, 2014. AN ESTIMATED 17.97 BARRELS OF ULTRALOW SULFUR DIESEL WERE RELEASED. AN ESTIMATED 17 BARRELS WERE RECOVERED NO ADDITIONAL REMEDIATION IS EXPECTED. 7/1/2016: CORRECTED GPS COORDINATES IN PART A5 AND SELECTED UNKNOWN FOR DATE INSTALLED IN PART C4 7/7/2016: UPDATED PART B5 TO REFLECT THE CORRECT COUNTY OF SAGINAW

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in