"BUCKEYE PARTNERS, LP"
hazardous_liquid Incident — — July 22, 2016
Incident Information
| Incident Date | July 22, 2016 |
| Operator | "BUCKEYE PARTNERS, LP" |
| Commodity | REFINED AND/OR PETROLEUM PRODUCT (NON-HVL) WHICH IS A LIQUID |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 41.60656, -87.46235 |
Cause
| Cause | INCORRECT OPERATION |
| Subcause | EQUIPMENT NOT INSTALLED PROPERLY |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | $1,000 |
| Emergency Response | $23,000 |
| Other Costs | $0 |
Location Map
Incident Narrative
"A RELEASE OF ULSD WAS OBSERVED BY A EMPLOYEE OF THE RAILROAD. THE RAILROAD EMPLOYEE IMMEDIATELY CONTACTED BUCKEYE'S CONTROL CENTER. THE PIPELINE CONTROLLER SHUTDOWN THE PIPELINE AND THIS SHUT DOWN STOPPED THE RELEASE. LOCAL OPERATIONS ARRIVED ON SITE AT 1947 AND CONFIRMED THE ULSD RELEASE. NRC WAS NOTIFIED AT 2138. THE RELEASE IMPACTED THE JUNCTION AND ADJACENT AREAS AS WELL AS SOME OF THE NEARBY IHB TRACKS. ALL REQUIRED NOTIFICATIONS WERE MADE. THE FAILED GASKET WAS REPLACED AND THE LINE WAS RESTARTED. ALL CONTAMINATED SOIL WAS PICKED UP AND DISPOSED OF. 85 YARDS OF SOIL WAS REMOVED. THE GASKET FAILED DUE TO INCORRECT INSTALLATION. DURING THE INSTALLATION OF A SKILLET THERE WAS DIFFICULTY GETTING THE FLANGES SPREAD AND LINED BACK UP. THE SPACE BETWEEN THE FLANGES WAS NOT LARGE ENOUGH TO INSERT A 3/4 SKILLET AS WELL AS TWO FLEXITALIC GASKETS. UNEVEN PRESSURES WAS PLACED ON ONE OF THE GASKETS BEFORE IT WAS BOLTED UP. AS A RESULT, UNEVEN/OVER COMPRESSION OF SECTIONS OF THE GASKET TOOK PLACE, WHICH DAMAGED THE GASKET AND CAUSED IT TO FAIL WHEN PIPELINE PRESSURE WAS RESTORED."