hazardous_liquid Incident —
Incident Information
| Report Date | — |
| Operator | MARATHON PIPE LINE LLC |
| Commodity | — |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 29.33678, -94.95822 |
Cause
| Cause | INCORRECT OPERATION |
| Subcause | — |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | — |
| Lost Commodity | — |
| Public/Private Damage | — |
| Emergency Response | — |
| Environmental Remediation | — |
| Other Costs | — |
Location Map
Incident Narrative
MPL PERSONNEL ARRIVED ON SITE AT APPROXIMATELY 09:00 CST TO REPACK THE HIGHLAND BAYOU BV. THE BLOCK VALVE WAS CLOSED AND THE BODY RELIEF VALVE WAS THEN OPENED TO REMOVE PRESSURE FROM THE BLOCK VALVE. THE EMPLOYEE BELIEVED THE BODY RELIEF VALVE TO BE MALFUNCTIONING AND DID NOT CLOSE THE VALVE. PERSONNEL THEN LEFT THE AREA DUE TO SAFETY CONCERNS. THE LINE WAS SHUT DOWN AND ONCE THE AREA WAS DEEMED SAFE, PRESSURE WAS REMOVED FROM THE LINE. THE FITTING WAS REPLACED WHILE THE LINE WAS DOWN AND THEN RETURNED TO NORMAL OPERATIONS. NO IMPACT TO SOIL. UPON FURTHER INVESTIGATION, THE BODY RELIEF VALVE WAS DETERMINED TO BE FIT FOR SERVICE. THE CAUSE OF THE INCIDENT IS CONSIDERED TO BE INCORRECT OPERATIONS. MPL REPORTED THE QUANTITY RELEASED AS ""UNKNOWN"" ON THE INITIAL NRC REPORT (#1127964). A SECOND REPORT (#1128048) WAS MADE TO UPDATE THE VOLUME TO 50 BARRELS. ADDITIONALLY, THE ESTIMATED 1,338 BBLS THAT WERE RELEASED DURING THE CONTROLLED BLOWDOWN TO REMOVE PRESSURE FROM THE LINE WERE DONE SO THROUGH A TEMPORARY FLARE SYSTEM. 5/7/19 - UPDATED GPS COORDINATES IN PART A