MARATHON PIPE LINE LLC

hazardous_liquid Incident — — September 13, 2017

Incident Information

Incident DateSeptember 13, 2017
OperatorMARATHON PIPE LINE LLC
CommodityREFINED AND/OR PETROLEUM PRODUCT (NON-HVL) WHICH IS A LIQUID
Pipeline Typehazardous_liquid

Location

State
Coordinates39.79832, -86.32292

Cause

CauseINCORRECT OPERATION
SubcauseDAMAGE BY OPERATOR OR OPERATOR'S CONTRACTOR NOT RELATED TO EXCAVATION AND NOT DUE TO MOTORIZED VEHICLE/EQUIPMENT DAMAGE

Casualties

Fatalities0
Injuries0

Costs

Property Damage$9,912
Emergency Response$27,512
Other Costs$0

Location Map

Incident Narrative

"ON SEPTEMBER 13, 2017, CONTRACT CREWS WERE ON-SITE PERFORMING A PROJECT TO REMOVE A CASING. WHILE DRILLING THROUGH THE CASING, THE CONTRACTOR DRILLED A HOLE INTO THE PIPE, RESULTING IN A RELEASE OF LIQUID NATURAL GASOLINE. APPROXIMATELY SIX BARRELS WERE RELEASED INTO THE EXCAVATION TRENCH. ALL PRODUCT WAS IMMEDIATELY CLEANED UP AND REPAIRS WERE MADE. THE CAUSE OF THIS RELEASE WAS INCORRECT OPERATIONS. AS A RESULT OF THIS RELEASE, FUTURE CASING REMOVAL PROJECTS WERE IMMEDIATELY SUSPENDED UNTIL PROCEDURES WERE IMPROVED. 2/8/18 UPDATE: PART C, QUESTION 3A. - CORRECTED THE NOMINAL DIAMETER TO 8 INCHES. PART C, QUESTION 6 - CHANGED THE TYPE OF ACCIDENT INVOLVED FROM ""OTHER"" TO ""LEAK""."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in