MARATHON PIPE LINE LLC

hazardous_liquid Incident — — December 12, 2017

Incident Information

Incident DateDecember 12, 2017
OperatorMARATHON PIPE LINE LLC
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates36.97082, -94.31477

Cause

CauseINCORRECT OPERATION
SubcauseOTHER INCORRECT OPERATION

Casualties

Fatalities0
Injuries0

Costs

Property Damage$0
Emergency Response$1,300
Other Costs$0

Location Map

Incident Narrative

"ON DECEMBER 12, 2017, PERSONNEL WERE ON-SITE, COMPLETING PROJECT WORK TO DRAIN DOWN AN OUT-OF-SERVICE PUMP WHEN THE RELEASE OCCURRED. THE VENT VALVE ON TOP OF THE PUMP WAS CONNECTED VIA TUBING TO THE PUMP SEAL CAVITY, AS A MEANS OF PROVIDING THERMAL PROTECTION FOR UNIT 4 WHICH WAS OUT-OF-SERVICE AT THE TIME. WHEN THE UNIT SUCTION AND DISCHARGE VALVES WERE OPENED, PRODUCT FILLED THE UNIT AND FLOWED THROUGH THE VENT VALVE, OVERWHELMING THE PUMP SEAL CAVITY DRAIN. INVESTIGATION FINDINGS INDICATE THE CAUSE WAS DUE TO A PROJECT-SPECIFIC PROCEDURE THAT WAS INADEQUATE. PROCEDURE IMPROVEMENTS ARE BEING CONSIDERED FOR FUTURE PROJECT WORK. 2/27/18: PART C, QUESTION 3 - UPDATED ITEM INVOLVED TO ""OTHER - OVERFLOWED PUMP SEAL CAVITY"". PART C, QUESTION 4 - UPDATED THE YEAR INSTALLED TO 1949. PART D, QUESTION 7 - CORRECTED OUR RESPONSE TO ""NO"". PART H - UPDATED THE NARRATIVE WITH INVESTIGATION RESULTS."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in