"ONEOK NGL PIPELINE, LLC"

hazardous_liquid Incident — — May 10, 2018

Incident Information

Incident DateMay 10, 2018
Operator"ONEOK NGL PIPELINE, LLC"
CommodityHVL OR OTHER FLAMMABLE OR TOXIC FLUID WHICH IS A GAS AT AMBI
Pipeline Typehazardous_liquid

Location

State
Coordinates35.78150, -97.23781

Cause

CauseOTHER OUTSIDE FORCE DAMAGE
SubcauseOTHER OUTSIDE FORCE DAMAGE

Casualties

Fatalities0
Injuries0

Costs

Property Damage$10
Emergency Response$112
Other Costs$0

Location Map

Incident Narrative

"AT APPROXIMATELY 7:30 ON 5/10/2018 ONEOK FIELD REPRESENTATIVE WAS CONTACTED BY CONTRACT CREW WORKING AT OENOK'S NEW FALL CREEK JUNCTION SITE TO REPORT VAPORS COMING FROM A 1/2"" PIPE NIPPLE ON A DOUBLE BLOCK AND BLEED VALVE ON THE METER SKID. ONEOK REPRESENTATIVE ARRIVED ON SITE AT APPROXIMATELY 8:00 AM AND ISOLATED THE VALVE AND REMOVED AND REPLACED THE FAILED PIPE NIPPLE. AN ELEVATED ACCESS PLATFORM HAD BEEN INSTALLED PRIOR TO HEAVY RAIN IN THE AREA AND AS A RESULT OF THE RAINFALL, SETTLED IN THE DIRT, ALLOWING THE SIDE OF THE PLATFORM TO CONTACT THE PIPE NIPPLE ON THE DOUBLE BLOCK AND BLEED VALVE WHICH CAUSED THE NIPPLE TO CRACK CAUSING THE RELEASE OF HYDROCARBONS. THE PLATFORM WAS MODIFIED AND RELOCATED TO PREVENT A REPEAT OF THIS TYPE OF ACCIDENT."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in