BUCKEYE PARTNERS, LP

hazardous_liquid Incident —

Incident Information

Report Date
OperatorBUCKEYE PARTNERS, LP
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates39.71265, -89.25084

Cause

CauseEQUIPMENT FAILURE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

DURING A STATION CHECK, THE INBOUND PIG TRAP DOOR WAS FOUND TO BE LEAKING. THE PIG TRAP WAS ISOLATED AND LOCKED OUT. ALL REQUIRED NOTIFICATIONS WERE MADE. IT WAS DETERMINED THAT A GASKET WAS LEAKING. OPERATIONS ADDRESSED DOOR GASKET ISSUE. 10 DRUMS OF CONTAMINATED SOIL WAS REMOVED.