BUCKEYE PARTNERS, LP

hazardous_liquid Incident —

Incident Information

Report Date
OperatorBUCKEYE PARTNERS, LP
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates41.78989, -86.25806

Cause

CauseINCORRECT OPERATION
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

DURING A TERMINAL INSPECTION, A RELEASE FROM THE BODY BLEED PIPING OF A DOUBLE BLOCK AND BLEED VALVE ON THE SUCTION VALVE TO THE BOOSTER, PUMPING FROM TANK 1 WAS FOUND. ALL THE REQUIRED INTERNAL AND EXTERNAL NOTIFICATION WERE MADE. ALL CONTAMINATED SOIL WAS REMOVED AND DRUMMED FROM DISPOSAL. IT WAS DETERMINED THAT THE VALVES ON THE BODY BLEED PIPING WERE INCORRECTLY ALIGNED. 12/20/2017 THE SOURCE OF THE RELEASE WAS A VALVE THAT WAS INSTALLED IN 2012 ON A TANK DURING A 653 INSPECTION. THE TANK WAS NOT PLACED BACK INTO SERVICE UPON COMPLETION DUE TO BUSINESS NEEDS. THE VALVE WAS EQUIPPED WITH A BODY RELIEF NEEDLE CHECK VALVE. LOCAL OPERATORS DID NOT VERIFY VALVE POSITIONING ON THE RELIEF SYSTEM WHEN THE TANK WAS RETURNED TO SERVICE. THE NEEDLE CHECK VALVE WAS LEFT IN THE OPEN POSITION ALLOWING DIESEL FUEL TO RELEASE THROUGH THE TEST FITTING, WHICH WAS NOT PLUGGED AT THE TIME OF DISCOVERY.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in