COLONIAL PIPELINE CO

hazardous_liquid Incident —

Incident Information

Report Date
OperatorCOLONIAL PIPELINE CO
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates31.64400, -89.51874

Cause

CauseCORROSION FAILURE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON THURSDAY SEPTEMBER 7, 2017 AT 08:00 CST A COLONIAL TECHNICIAN PERFORMING A FACILITY CHECK OBSERVED STAINED GRAVEL IN THE AREA OF THE LINE-2 UNIT #3 DRAIN VALVE. AFTER FURTHER INVESTIGATION PRODUCT WAS FOUND IN AN ACCESS WELL LOCATED BESIDE THE UNIT #3 DISCHARGE VALVE. IMMEDIATELY AFTER DISCOVERING THE PRODUCT, AT APPROXIMATELY 08:08, THE TECHNICIAN COMPLETED THE REQUIRED INTERNAL NOTIFICATIONS. AFTER ADDITIONAL RESOURCES ARRIVED ON SITE AND CONDUCTED FURTHER INVESTIGATION, PRODUCT WAS ALSO DISCOVERED IN THE FACILITY OIL/WATER SEPARATOR AND A NEARBY FACILITY MONITORING WELL. THE SYSTEM CONTROLLER SHUTDOWN AND ISOLATED THE STATION AT 10:08. RESPONSE PERSONNEL ON SITE EVALUATING THE SITUATION AND THE POTENTIAL LEVEL OF EXPLORATORY EXCAVATION IT COULD TAKE TO FIND THE PRODUCT SOURCE DEEMED THAT THE INCIDENT COST MIGHT EXCEED $50,000. THEREFORE, THE DECISION WAS MADE TO COMPLETE THE NRC NOTIFICATION AND THE REPORT WAS FILED AT 16:23. HYDRO EXCAVATION OF THE SUSPECTED LEAK AREA PROMPTLY IDENTIFIED THE LEAK SOURCE TO BE A PINHOLE WITHIN THE FACILITY 4 INCH PIPE DRAIN SYSTEM. AS A TEMPORARY REPAIR UNTIL A FINAL REPAIR SOLUTION IS DETERMINED, A PLIDCO CLAMP WAS INSTALLED. ALL FREE STANDING PRODUCT AND CONTAMINATED SOIL WAS CLEANED UP THE STATION WAS RESTARTED 18:31. THERE WERE NO REQUIRED NOTIFICATIONS FOR STATE AND/OR LOCAL AGENCIES, ALTHOUGH A COURTESY NOTIFICATION WAS MADE TO THE MDEQ. JANUARY 2018 SUPPLEMENT REPORT PROVIDES UPDATES TO THE FOLLOWING: PART A, 9 AND 11: UPDATED RELEASED AND RECOVERED VOLUMES. PART D, 3: YES TO LONG TERM IMPACT ASSESSMENT PERFORMED OR PLANNED. PART D, 4: YES TO ANTICIPATED REMEDIATION. PART D, 5 AND 5(A) AND 5(B): ADDED WATER CONTAMINATION AND SPECIFIED GROUNDWATER AND VOLUME. PART D, 8: REVISED COST ESTIMATES BASED ON MOST CURRENT INFORMATION. PART E, 2: CORRECTED MOP A FINAL REPORT WILL BE SUBMITTED WITHIN 30 DAYS FOLLOWING THE COMPLETION OF THE INCIDENT ANALYSIS. FINAL REPORT UPDATE: INCIDENT ANALYSIS WAS COMPLETED AND APPROVED ON 2 MAY 2018. NO ADDITIONAL INFORMATION DETERMINED ON APPARENT CAUSE. THE PLIDCO CLAMP HAS BEEN APPROVED AS THE FINAL REPAIR.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in