"COUNTRYMARK REFINING AND LOGISTICS, LLC"

hazardous_liquid Incident — — August 31, 2019

Incident Information

Incident DateAugust 31, 2019
Operator"COUNTRYMARK REFINING AND LOGISTICS, LLC"
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates38.66464, -88.32363

Cause

CauseMATERIAL FAILURE OF PIPE OR WELD
Subcause"DESIGN-, CONSTRUCTION-, INSTALLATION-, OR FABRICATION-RELATED"

Casualties

Fatalities0
Injuries0

Costs

Property Damage$7,000
Emergency Response$17,000
Other Costs$0

Location Map

Incident Narrative

"AT APPROXIMATELY 05:20 AM CST ON SEPTEMBER 1 THE GAUGER CAME TO CLAY CITY STATION TO TAKE INVENTORY. HE NOTICED OIL SPRAYING FROM AROUND THE PUMP AREA. HE IMMEDIATELY NOTIFIED THE CONTROL ROOM. THE OPERATIONS SUPERVISOR WAS IN THE CONTROL ROOM WITH THE CONTROLLER. THE GAUGER RELAYED THAT THE LEAK WAS COMING FROM A CRACK IN A WELD ON A 2"" BRANCHED FITTING AND APPROXIMATE AMOUNT OF LOST OIL TO THE CONTROLLER AND OPERATIONS SUPERVISOR. THE CONTROL ROOM SHUT IN THE TANK 421 OUTLET MOV, 421-V2, AND DOWNSTREAM LAUNCHER BY-PASS MOV 03-TBV TO ISOLATE THE LEAK AND SLOW THE LEAK. THE OPERATIONS SUPERVISOR THEN NOTIFIED THE MAINTENANCE MANAGER AND MAINTENANCE SUPERVISOR OF THE INCIDENT AND WHAT RESOURCES WOULD BE REQUIRED. RESOURCES ARRIVED AT APPROXIMATELY 06:30 AM TO BEGIN RESPONSE ACTIVITIES. THE LEAKING SECTION WAS REPLACED AND THE PIPELINE STARTED BACK UP LATER THAT EVENING. CLEAN-UP ACTIVITIES CONTINUED THE NEXT 2 DAYS UNTIL ALL OIL HAD BEEN RECOVERED. THE FAILED FITTING WAS SENT TO A MATERIALS TESTING LAB FOR FAILURE ANALYSIS."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in