ONEOK NGL PIPELINE, LLC

hazardous_liquid Incident —

Incident Information

Report Date
OperatorONEOK NGL PIPELINE, LLC
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates34.18890, -96.48450

Cause

CauseINCORRECT OPERATION
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

AT APPROXIMATELY 11:26 ON 4/12/2018 ONEOK'S FIELD REPRESENTATIVE CALLED THE ONEOK PIPELINE CONTROL CENTER TO REPORT THE LANDOWNER AROUND ONEOK'S BLUE RIVER PUMP STATION HAD NOTIFIED HIM OF 'STEAM' COMING FROM THE ABOVEGROUND PIPING AT THE PUMP STATION. ONEOK'S FIELD REPRESENTATIVE ARRIVED ON SITE AT APPROXIMATELY 12:52 AND DETERMINED VAPORS WERE COMING FROM THE GASKET BETWEEN TWO FLANGES CONNECTED TO THE STATION DISCHARGE VALVE. THE PUMP STATION WAS SHUT DOWN AND ONEOK MECHANICS WERE CALLED TO RE-TORQUE THE BOLTS ON THE FLANGES. ONCE THE BOLTS WERE TIGHTENED TO THE TORQUE SPECIFICATIONS FOR THE FIBER GASKET THE PUMP STATION WAS RETURNED TO SERVICE AND NO LEAKS WERE IDENTIFIED. THIS PIPING HAD BEEN RECENTLY CHANGED OUT, DUE TO MAINTENANCE WORK AT THE FACILITY. ONEOK'S INVESTIGATION DETERMINED CONTRACTORS TIGHTENING THE BOLTS ON THE FLANGES, AFTER THE CHANGE OUT, UTILIZED THE TORQUEING REQUIREMENTS FOR METAL GASKETS INSTEAD OF TORQUEING REQUIREMENTS FOR THE FIBER GASKET. THIS RESULTED IN THE BOLTS BEING UNDER TIGHTENED. ONEOK REPRESENTATIVES MET WITH THE CONTRACTOR AND INSPECTOR THAT WORKED ON THE PROJECT AND EMPHASIZED THE IMPORTANCE OF INSURING THE CORRECT TORQUE SPECIFICATIONS ARE UTILIZED.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in