"ONEOK NGL PIPELINE, LLC"

hazardous_liquid Incident — — October 22, 2019

Incident Information

Incident DateOctober 22, 2019
Operator"ONEOK NGL PIPELINE, LLC"
CommodityHVL OR OTHER FLAMMABLE OR TOXIC FLUID WHICH IS A GAS AT AMBI
Pipeline Typehazardous_liquid

Location

State
Coordinates36.77402, -97.75716

Cause

CauseEQUIPMENT FAILURE
SubcauseTHREADED CONNECTION/COUPLING FAILURE

Casualties

Fatalities0
Injuries0

Costs

Property Damage$6,400
Emergency Response$500
Other Costs$0

Location Map

Incident Narrative

"ON 10/22/19 AT 3:50 AM, PLANT OPERATORS IDENTIFIED VAPOR LEAKING FROM A 3/4"" THREADED NIPPLE ON STERLING 2 PUMP HEADER. PUMP HEADER ISOLATED AND PRODUCT REMOVED. ONEOK REPLACED FAILED 3/4"" NIPPLE AND ASSOCIATED BALL VALVE. PIPELINE WAS RETURNED TO SERVICE. ONEOK DETERMINED PIPE NIPPLE FAILED DUE TO HIGH CYCLE FATIGUE (VIBRATION) CAUSED BY THE PIPELINE CONTROL VALVE. ONEOK CONDUCTED VIBRATION STUDY AFTER INSTALLATION OF NEW PIPELINE CONTROL VALVE AND VIBRATION WAS REDUCED TO AN ACCEPTABLE LEVEL. ADDITIONALLY, ONEOK REPLACED ALL SIMILAR THREADED NIPPLES ON THE STERLING 2 PIPELINE HEADER SYSTEM."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in