"BUCKEYE PARTNERS, LP"

hazardous_liquid Incident — — November 30, 2019

Incident Information

Incident DateNovember 30, 2019
Operator"BUCKEYE PARTNERS, LP"
CommodityREFINED AND/OR PETROLEUM PRODUCT (NON-HVL) WHICH IS A LIQUID
Pipeline Typehazardous_liquid

Location

State
Coordinates42.28255, -83.14096

Cause

CauseEQUIPMENT FAILURE
SubcausePUMP OR PUMP-RELATED EQUIPMENT

Casualties

Fatalities0
Injuries0

Costs

Property Damage$24,854
Emergency Response$45,004
Other Costs$0

Location Map

Incident Narrative

"ON NOVEMBER 30, 2019 BUCKEYE PERSONNEL DISCOVERED A PRODUCT RELEASE FROM A LOW SPEED BOOSTER TANK PUMP. THE PUMP WAS ISOLATED. INTERNAL AND EXTERNAL NOTIFICATIONS WERE MADE. CLEAN UP ACTIVITIES WERE CONDUCTED AND THE PUMP WAS PUT BACK IN SERVICE. THE INVESTIGATION FOUND THAT THE MOTOR BEARINGS WAS INSTALLED BACKWARD. INSTALLATION WAS CONDUCTED BY PREVIOUS DETROIT TERMINAL OWNER. THIS ALLOWED THE IMPELLER TO LIFT UPWARD ON PUMP START UP. THE UPWARD LIFT OF THE IMPELLER ALLOWED THE PUMP CASE RING AND IMPELLER TO RUB THAT PRODUCE METAL SHAVING, THE SHAVINGS DAMAGED THE PUMP THROTTLE BUSHING TO SHAFT AND PUMP SEAL THAT RESULTED IN THE PRODUCT RELEASE. IN THE COURSE OF THE INVESTIGATION, BUCKEYE DETERMINED THE SPILL COST EXCEEDED $50,000 AND NOTIFIED THE NRC ACCORDINGLY. THE COST EXCEEDANCE WAS NOT FORESEEABLE AND UNEXPECTED."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in