FRONT RANGE PIPELINE, LLC.

hazardous_liquid Incident — — March 4, 2019

Incident Information

Incident DateMarch 4, 2019
OperatorFRONT RANGE PIPELINE, LLC.
CommodityCRUDE OIL
Pipeline Typehazardous_liquid

Location

State
Coordinates46.75569, -109.85751

Cause

CauseEQUIPMENT FAILURE
SubcauseNON-THREADED CONNECTION FAILURE

Casualties

Fatalities0
Injuries0

Costs

Property Damage$15,000
Emergency Response$200,000
Other Costs$1,000

Location Map

Incident Narrative

AT 17:08 ON 3/4/19 THE PILOT CONTACTED LOCAL OPERATING PERSONNEL/CONTROL ROOM TO NOTIFY THEM OF A POTENTIAL RELEASE NEAR JUDITH GAP PUMP STATION. THE CONTROLLER SHUTDOWN THE PIPELINE AT 17:12 AND DID NOT RECEIVE ANY SCADA OR LEAK DETECTION ALARMS RELATED TO THE RELEASE. THE LEAK DETECTION DID NOT ALARM DUE TO LEAK RATE TRIGGERS NOT BEING MET. DUE TO POOR WEATHER CONDITIONS AND DRIFTING SNOW, FIELD PERSONAL ARRIVED ON-SITE AT 19:25. THE RELEASE ORIGINATED FROM FAILURE OF A GASKET IN A BOLTED FLANGE ON A CHECK VALVE. THE GASKET WAS REPLACED AND THE PIPELINE WAS RETURNED TO FULL OPERATION AT 15:11 ON 3/6. THE INCIDENT INVESTIGATION CONCLUDED THAT A SPIRAL WOUND GASKET THAT WAS NOT EQUIPPED WITH AN INNER RING CAME UNWOUND. THE VALVE VAULT CONTRIBUTED TO THE SEVERITY OF THE RELEASE BY IMPACTING THE DETECTION TIME.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in