WYOMING PIPELINE COMPANY
hazardous_liquid Incident — — March 6, 2019
Incident Information
| Incident Date | March 6, 2019 |
| Operator | WYOMING PIPELINE COMPANY |
| Commodity | CRUDE OIL |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 43.82592, -104.32507 |
Cause
| Cause | EQUIPMENT FAILURE |
| Subcause | THREADED CONNECTION/COUPLING FAILURE |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | $1,000 |
| Emergency Response | $20,000 |
| Other Costs | $0 |
Location Map
Incident Narrative
AT APPROXIMATELY 23:00 P.M. ON WEDNESDAY, MARCH 6, 2019, THE OPERATIONS CONTROL CENTER NOTICED A DEFICIENCY IN THE VOLUME OF OIL BETWEEN THE MUSH CREEK PUMPING STATION AND THE REFINERY. THE ON-CALL PIPELINE PERSON WAS CALLED TO INVESTIGATE. WHILE CHECKING FOR LEAKS, HE NOTICED THAT A PIPE NIPPLE USED TO CONNECT A PRESSURE TRANSMITTER TO THE PIPELINE HAD BROKEN OFF THE PIPE AT BUTTE JUNCTION. THE PIPELINE WAS THEN SHUT DOWN. CLEAN-UP STARTED THE NEXT MORNING AROUND 6:00 A.M. VACUUM TRUCKS WERE USED TO CLEAN UP FREE STANDING LIQUIDS AND A BACKHOE WAS USED TO COLLECT CONTAMINATED SNOW. CONTAMINATED SNOW AND SOIL WAS BE PLACED IN A PLASTIC LINED BERMED .. SOIL WILL BE SAMPLED AND DISPOSED OF ACCORDINGLY. EXPANSION/VIBRATION LOOPS WERE INSTALLED BETWEEN THE MAINLINE AND PRESSURE TRANSMITTED TO ELIMINATE VIBRATION.