MAGELLAN PIPELINE COMPANY, LP
hazardous_liquid Incident —
Incident Information
| Report Date | — |
| Operator | MAGELLAN PIPELINE COMPANY, LP |
| Commodity | — |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 36.14799, -96.03286 |
Cause
| Cause | EXCAVATION DAMAGE |
| Subcause | — |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | — |
| Lost Commodity | — |
| Public/Private Damage | — |
| Emergency Response | — |
| Environmental Remediation | — |
| Other Costs | — |
Location Map
Incident Narrative
AT 14:28 ON JUNE 8, 2020, MAGELLAN'S TULSA - BARNSDALL #4-12"" PIPELINE WAS IMPACTED BY A SECOND PARTY LINE STRIKE DURING HORIZONTAL DIRECTIONAL DRILLING OPERATION. AT THE TIME OF THE INCIDENT, MAGELLAN'S CONTRACTOR WAS PERFORMING THE PILOT HOLE OPERATION FOR THE #3-12"" PIPELINE REPLACEMENT ACROSS THE ARKANSAS RIVER AND STRUCK THE #4-12"" PIPELINE NORTH OF THE ARKANSAS RIVER BETWEEN THE NORTH LEVEE AND CHARLES PAGE BLVD. CODE RED RESPONSE WAS INITIATED AND FIELD PERSONNEL WERE DISPATCHED TO FURTHER ISOLATE THE BLOCKED IN SECTION WITH MANUAL VALVES AND BEGIN CLEANUP ACTIVITIES. AT THE TIME OF THE INCIDENT, THE PIPELINE WAS SHUT DOWN AND ISOLATED WITH REMOTE ISOLATION VALVES. THE #4-12"" PIPELINE WAS RETURNED TO SERVICE BY COMMISSIONING A NEWLY INSTALLED HDD REPLACEMENT CROSSING FOR THE #1-12"". THE IMPACTED PIPELINE SEGMENT WILL BE GROUT FILLED AND ABANDONED IN PLACE. THE PUNCTURE SIZE IS AN ESTIMATE BASED ON RELEASE VOLUME. NRC 48-HOUR UPDATE: #1279210, 06/09/14:12 SUPPLEMENTAL/FINAL:(09/11/2020) PART A11, D8, E9, G3-17, H
About This Pipeline Incident
Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.