FLINT HILLS RESOURCES, LC

hazardous_liquid Incident —

Incident Information

Report Date
OperatorFLINT HILLS RESOURCES, LC
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates27.81538, -97.48873

Cause

CauseNATURAL FORCE DAMAGE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON MARCH 1, 2021, FLINT HILLS RESOURCES (FHR) STARTED THE P8A LATERAL FOR THE FIRST TIME AFTER A RECORD FREEZE EVENT. AT 15:33, FHR OPERATIONS AND CONTROL CENTER PERSONNEL DETERMINED THAT LINE PACKING WAS TAKING LONGER THAN ANTICIPATED, SHUT DOWN THE LINE, AND INITIATED INVESTIGATION. AT 15:40, FHR PERSONNEL ARRIVED ONSITE, DISCOVERED A RELEASE, AND ISOLATED THE LATERAL. FHR PERSONNEL ISOLATED THE METER SKID AT 16:00. THE RELEASE STOPPED AT 19:06 AND FHR PERSONNEL REMOVED THE 2-INCH DRAIN VALVE AND INSTALLED A BLIND FLANGE AT 20:10. FHR REPLACED THE 2-INCH DRAIN VALVE ON MARCH 2. BASED ON BUSINESS NEEDS, THE LATERAL WAS RE-STARTED ON MARCH 11. FHR WILL SEND THE 2-INCH DRAIN VALVE TO A THIRD PARTY FOR FURTHER EVALUATION. UPDATE PART H (JUNE 2021) - DUE TO AN EXTENDED RECORD FREEZE EVENT, POWER GRID OUTAGES, AND ASSOCIATED PLANT OUTAGES, MOISTURE IN THE VALVE BODY FROZE AND EXPANDED CAUSING VALVE BODY STUDS TO STRETCH. THIS RESULTED IN VALVE BODY TO TAIL PIECE MISALIGNMENT CREATING A GAP ON THE INTERNAL GASKET SEALING SURFACE. THIS GAP ALLOWED FOR AN EXTERNAL LEAK PATH.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in