NUSTAR PIPELINE OPERATING PARTNERSHIP L.P.

hazardous_liquid Incident — — July 27, 2023

Incident Information

Incident DateJuly 27, 2023
OperatorNUSTAR PIPELINE OPERATING PARTNERSHIP L.P.
CommodityHVL OR OTHER FLAMMABLE OR TOXIC FLUID WHICH IS A GAS AT AMBI
Pipeline Typehazardous_liquid

Location

State
Coordinates33.26331, -92.68999

Cause

CauseMATERIAL FAILURE OF PIPE OR WELD
SubcauseORIGINAL MANUFACTURING-RELATED (NOT GIRTH WELD OR OTHER WELDS FORMED IN THE FIELD)

Casualties

Fatalities0
Injuries0

Costs

Property Damage$108,800
Emergency Response$0
Other Costs$0

Location Map

Incident Narrative

"AT 11:13 EDC PERSONNEL NOTIFIED NUSTAR OF A POSSIBLE AMMONIA LEAK BUBBLING UP UNDER THEIR RETENTION POND. THE PIPELINE WAS ALREADY SHUT DOWN DUE TO A PLANNED HYDROTEST FROM PEACE VALLEY, AR TO SALEM, MO. LOCAL PERSONNEL ARRIVED ON-SITE AT 11:48 AND CONFIRMED A LEAK, ISOLATED THE PIPELINE BY CLOSING MANUAL VALVES AND VERIFIED THAT AN MOV (23-4) WAS CLOSED. IN THAT AREA THERE IS AROUND 741 FEET BETWEEN MANUAL VALVES WITH AN ESTIMATED 2500 POUNDS THAT WAS RELEASED DURING THE EVENT. NO VAPOR CLOUD PRESENT AS IT WAS BEING RELEASED INTO THE RETENTION POND. THE RETENTION POND IS USED BY EDC TO HOLD THEIR PROCESS WASTEWATER. METALLURGICAL ANALYSIS CONCLUDED, ""THE FAILURE WAS THE RESULT OF SELECTIVE SEAM WELD CORROSION (SSWC). MULTIPLE WELD DEFECTS, INCLUDING LACK OF FUSION (LOF), WERE OBSERVED AT THE INNER DIAMETER (ID)."

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.