CRESCENT MIDSTREAM, LLC

hazardous_liquid Incident —

Incident Information

Report Date
OperatorCRESCENT MIDSTREAM, LLC
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates29.26058, -89.19948

Cause

CauseINCORRECT OPERATION
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

CRESCENT CONDUCTED A HYDROTEST ON THE DELTA NORTH 2 PIPELINE PRIOR TO THE INCIDENT. DURING THE HYDROTEST IT WAS DETERMINED THAT VALVES ON THE SSTI ASSEMBLY CONNECTING THE DELTA DUCK FACILITY TO CRESCENT'S DN2 PIPELINE DID NOT HOLD PRESSURE. A SUCCESSFUL HYDROTEST WAS CONDUCTED AFTER REMOVING A SPOOL PIECE FROM THE SSTI ASSEMBLY AND INSTALLING A BLIND FLANGE. THE ASSEMBLY WAS REASSEMBLED AND PRODUCT WAS RETURNED TO THE LINE AND A 2 HOUR STAND UP TEST WAS CONDUCTED. THE LINE WAS THEN RETURNED TO SERVICE AND DURING SITE CHECKS BY THE CONTRACT CREW, A SMALL SHEEN WAS OBSERVED ON THE WATER ABOVE THE ASSEMBLY AND PIPELINE. DIVERS WENT DOWN TO CONDUCT A SWAB TEST AND FOUND A COUPLE FITTINGS AND FLANGES WITH SMALL LEAKS. NEW VALVES WERE ORDERED AND DURING THE CONSTRUCTION ACTIVITIES TO REPLACE THE VALVES ON THE ASSEMBLY, CRUDE OIL WAS RELEASED. ALL ASSEMBLY VALVES WERE REPLACED AND THE PIPELINE HAS BEEN RETURNED TO SERVICE.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.