ENTERPRISE CRUDE PIPELINE LLC
hazardous_liquid Incident — — October 14, 2025
Incident Information
| Incident Date | October 14, 2025 |
| Operator | ENTERPRISE CRUDE PIPELINE LLC |
| Commodity | CRUDE OIL |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 32.02083, -101.98389 |
Cause
| Cause | MATERIAL FAILURE OF PIPE OR WELD |
| Subcause | "DESIGN-, CONSTRUCTION-, INSTALLATION-, OR FABRICATION-RELATED" |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | $8,490 |
| Emergency Response | $250 |
| Other Costs | $0 |
Location Map
Incident Narrative
"ON 10/14/2025 AT 10:45 AM CDT, ENTERPRISE MAINTENANCE TECHNICIAN, LOCATED A CRACKED SOC-O-LET WELD ON A 1-INCH THERMAL RELIEF BYPASS PIPING ON A LID C134 LOVING METER SKID AT MIDLAND TANK FARM. THE LEAK AREA HAS BEEN ISOLATED AND REMEDIATED. APPARENT CAUSE WAS IDENTIFIED AS A WELD FAILURE DUE TO EXCESSIVE VIBRATIONS. THE WELD WAS REPAIRED, AND PIPING WAS RETURNED TO SERVICE."
About This Pipeline Incident
Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.