"HOLLY ENERGY PARTNERS - OPERATING, L.P."
hazardous_liquid Incident — — December 3, 2025
Incident Information
| Incident Date | December 3, 2025 |
| Operator | "HOLLY ENERGY PARTNERS - OPERATING, L.P." |
| Commodity | REFINED AND/OR PETROLEUM PRODUCT (NON-HVL) WHICH IS A LIQUID |
| Pipeline Type | hazardous_liquid |
Location
| State | |
| Coordinates | 32.29978, -101.07455 |
Cause
| Cause | CORROSION FAILURE |
| Subcause | EXTERNAL CORROSION |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | $10,000 |
| Emergency Response | $15,000 |
| Other Costs | $0 |
Location Map
Incident Narrative
"ON DECEMBER 3, 2025, WHILE COMPANY PERSONNEL WERE STAKING LOCATIONS FOR A PLANNED PIPELINE REPLACEMENT PROJECT, SOIL STAINING WAS OBSERVED DIRECTLY ABOVE THE PIPELINE. AT APPROXIMATELY 2:43 P.M. CENTRAL TIME, THE OBSERVATION WAS REPORTED TO THE PIPELINE SUPERVISOR. AS A PRECAUTION, THE SUPERVISOR IMMEDIATELY CONTACTED THE ARTESIA CONTROL CENTER AND DIRECTED THE PIPELINE TO BE SHUT DOWN. FIELD PERSONNEL BEGAN HAND EXCAVATION, AND AT APPROXIMATELY 3:17 P.M. CENTRAL TIME, THE RELEASE WAS CONFIRMED TO BE ORIGINATING FROM THE PIPELINE. ADDITIONAL PERSONNEL WERE DISPATCHED FROM THE ABILENE TERMINAL, AND THE COMPANY