"DCP MIDSTREAM, LP"

gas_transmission Incident — — June 2, 2024

Incident Information

Incident DateJune 2, 2024
Operator"DCP MIDSTREAM, LP"
CommodityNATURAL GAS
Pipeline Typegas_transmission

Location

State
Coordinates36.46780, -101.23282

Cause

CauseOTHER INCIDENT CAUSE
SubcauseMISCELLANEOUS

Casualties

Fatalities0
Injuries0

Costs

Property Damage$1,628
Emergency Response$1,000
Other Costs$0

Location Map

Incident Narrative

EXTENDED OPERATION OF RELIEF VALVE BELOW PIPELINE MAOP DUE TO INCREASED GAS PRESSURE FROM MAINTENANCE PIGGING OPERATIONS. FOLLOWING RELEASE PSV TESTED AND CONFIRMED CORRECT OPERATION. PROJECT INITIATED TO ADD FLOW SENSORS TO THE RELIEF VALVE AND EVALUATE CONTROL LOGIC FOR SLUG CATCHER INLET CONTROL VALVES TO PREVENT FUTURE RELEASES.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in