SEA ROBIN PIPELINE CO
gas_transmission Incident — — November 17, 2025
Incident Information
| Incident Date | November 17, 2025 |
| Operator | SEA ROBIN PIPELINE CO |
| Commodity | NATURAL GAS |
| Pipeline Type | gas_transmission |
Location
| State | |
| Coordinates | 28.85277, -92.03222 |
Cause
| Cause | CORROSION FAILURE |
| Subcause | INTERNAL CORROSION |
Casualties
| Fatalities | 0 |
| Injuries | 0 |
Costs
| Property Damage | $791,500 |
| Emergency Response | $147,000 |
| Other Costs | $0 |
Location Map
Incident Narrative
"11-17-25 BSEE REPORTED A LEAK IN SMI 31 4 MILES NW OF OUR SMI 33 JUNCTION PLATFORM. ET PERSONNEL COMPLETED AN OVERFLIGHT TO VERIFY AND CONFIRM THE LOCATION OF THE POSSIBLE LEAK. NRC REPORT# 1448168 WAS MADE AT 13:55 11-17-25 DSV PROTEUS / REPAIR MATERIALS SOURCED THROUGH RUPE. THE CLAMP WAS LOCATED ON 11/17 BUT HAD TO HAVE REPAIRS MADE TO IT AND WAS NOT READY FOR DEPLOYMENT UNTIL AFTER THE 12/11 TESTING. NOTE: DUE TO WEATHER AND DSV AVAILABILITY, THE REPAIR CONTRACTOR WAS NOT ABLE TO DEPLOY UNTIL 1-15-26 OVERFLIGHTS CONDUCTED DAILY AS WEATHER PERMITS. 11-18-25 UPSTREAM AND DOWNSTREAM VALVES CLOSED ISOLATING THE 26
About This Pipeline Incident
Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.