DCP MIDSTREAM

hazardous_liquid Incident —

Incident Information

Report Date
OperatorDCP MIDSTREAM
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates39.74636, -104.67988

Cause

CauseEQUIPMENT FAILURE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON MAY 29 2013, AT (7:58AM CDST), DCP MIDSTREAM'S HOUSTON CONTROL CENTER (HCC) RECORDED AND RESPONDED TO ACTIVATION OF THE GAS DETECTOR ALARM, HAZARDOUS GAS ALARM AND MAIN BREAKER OPEN INDICATION AT THE DCP WATTENBERG PUMP STATION. THE HCC OPERATOR IMMEDIATELY CALLED THE DCP FIELD TECHNICIAN TO INFORM THEM OF THE ALARMS. THE FIELD TECHNICIAN INSTRUCTED THE HCC CONTROLLER TO ENSURE THAT THE STATION WAS SHUT-DOWN AND ISOLATED. A SECOND FIELD TECHNICIAN ARRIVED ON SITE (AT 7:01 AM MDST), AND THEY OBSERVED A VAPOR RELEASE COMING FROM A FLANGED CONNECTION. THE TECHNICIANS IMMEDIATELY ENSURED THE STATION ISOLATION VALVES WERE FULLY SEATED AND WAITED FOR THE PIPE SECTION TO HAVE A CONTROLLED RELEASE BEFORE ENTERING THE SITE OF THE FLANGED CONNECTION. THE DCP TECHNICIAN WAS ABLE TO RELEASE THE REMAINDER OF THE PRODUCT THROUGH A FLARE. THE SCRAPER LAUNCHER WAS ISOLATED AND THE RELEASE CONTAINED BY( 7:15AM MDST.) AFTER THE STATION HAD BEEN SECURED, THE DCP TECHNICIANS REMOVED THE FAILED COMPONENT. DURING THAT PROCESS THEY OBSERVED TWO OF THE FLANGE BOLTS ON THE WERE NOT ADEQUATELY TORQUED. THE FAILED COMPONENT WAS AN ANSI 6"" 900 SERIES NEOPRENE COATED PHENOLIC CP ISOLATION GASKET, THE GASKET WAS BROKEN IN TWO LOCATIONS (APPROXIMATELY 10 AND 2 OCLOCK).

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in