CENTURION PIPELINE L.P.

hazardous_liquid Incident —

Incident Information

Report Date
OperatorCENTURION PIPELINE L.P.
Commodity—
Pipeline Typehazardous_liquid

Location

State
Coordinates32.03189, -102.50421

Cause

CauseCORROSION FAILURE
Subcause—

Casualties

Fatalities0
Injuries0

Costs

Property Damage
Lost Commodity
Public/Private Damage
Emergency Response
Environmental Remediation
Other Costs

Location Map

Incident Narrative

ON FEBRUARY 10, 2020, AT 7:00AM, A CENTURION PIPELINE L.P. (CPL) EMPLOYEE DISCOVERED A LEAK FROM STATION PIPING WITHIN THE BOUNDARIES OF CPL'S ECTOR COUNTY STATION. APPROXIMATELY THREE (3) BARRELS OF OIL WERE RELEASED, ALL OF WHICH WERE RECOVERED EITHER IN LIQUID FORM OR FROM SOIL REMEDIATION. ALL REMEDIATION IS COMPLETE AND ALL PRODUCT IS REMOVED FROM THE ENVIRONMENT. SUBSEQUENT TO A VISUAL INSPECTION IT WAS DETERMINED THAT INTERNAL CORROSION WAS THE CAUSE OF THE LEAK. CPL HAS REMOVED THE AFFECTED PIPE AND INSTALLED A TEMPORARY PIPELINE WHICH WILL ITSELF BE REMOVED WHEN A STATION RE-CONFIGURATION TAKES PLACE WITHIN THREE MONTHS. AN INVESTIGATION IS ONGOING TO DETERMINE IF MICROBIOLOGICALLY-INDUCED CORROSION (MIC) MAY ALSO BE A CONTRIBUTING CAUSE. IF SO, A SUPPLEMENTAL REPORT WILL BE FILED AND THE INVESTIGATION FINDINGS WILL BE USED TO PREVENT FUTURE SIMILAR INCIDENTS FROM OCCURRING. SUPPLEMENTAL FINAL REPORT FILED ON APRIL 16, 2020: SINCE THE ORIGINAL REPORT WAS FILED ON MARCH 09, 2020, CPL HAS CONDUCTED A ROOT CAUSE FAILURE ANALYSIS AND CONFIRMED THE LEAK WAS CAUSED BY INTERNAL CORROSION. THIS INTERNAL CORROSION WAS CONSISTENT WITH MICROBIOLOGICALLY INFLUENCED CORROSION (MIC). THE FAILED PIPELINE HAD, DUE TO CHANGES IN FLOW CONDITIONS DICTATED BY MARKET FORCES, EXPERIENCED A PERIOD OF FLOW STAGNATION WHICH PERMITTED WATER TO SEPARATE FROM THE CRUDE OIL PRODUCT. THIS SEPARATION RESULTED IN FAVORABLE CONDITIONS FOR MIC TO FORM. AN UNRELATED EXPANSION PROJECT, TO BE CONSTRUCTED SOON, WILL RECONFIGURE THE STATION PIPING. THE NEW CONFIGURATION WILL PREVENT SIMILAR FAILURES FROM OCCURRING BY ELIMINATING PIPELINE PHYSICAL FEATURES CONDUCIVE TO MIC FORMATION.

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in