"MAGELLAN PIPELINE COMPANY, LP"

hazardous_liquid Incident — — April 2, 2020

Incident Information

Incident DateApril 2, 2020
Operator"MAGELLAN PIPELINE COMPANY, LP"
CommodityHVL OR OTHER FLAMMABLE OR TOXIC FLUID WHICH IS A GAS AT AMBI
Pipeline Typehazardous_liquid

Location

State
Coordinates37.79221, -96.88137

Cause

CauseCORROSION FAILURE
SubcauseEXTERNAL CORROSION

Casualties

Fatalities0
Injuries0

Costs

Property Damage$5,000
Emergency Response$10,000
Other Costs$0

Location Map

Incident Narrative

"AT 11:34 AM ON APRIL 2, 2020 MAGELLAN FIELD PERSONNEL WERE NOTIFIED BY A CONTRACTOR OF VAPOR BUBBLING UP OVER MAGELLAN'S ONEOK TO ENTERPRISE PIPELINE. MAGELLAN PERSONNEL ARRIVED ONSITE, CONTACTED THE OPERATIONS CONTROL CENTER AND BEGAN EXCAVATION OF THE PIPELINE. A PINHOLE FAILURE WAS DISCOVERED IN IN AN AREA OF DISBONDED COATING. A PLIDCO CLAMP WAS INSTALLED TO STOP THE RELEASE AND CONTAMINATED SOIL WAS EXCAVATED, SAMPLED, AND PLACED IN ROLL OFF CONTAINERS FOR DISPOSAL. THIS LINE WAS SHUT-IN AT THE TIME OF THE RELEASE. A PROJECT IS IN PROGRESS TO REPAIR THE FAILURE WITH A SLEEVE OR PIPE REPLACEMENT. BASED ON OPERATIONAL NEEDS, THE LINE WILL ALSO BE PURGED WITH NITROGEN. SUPPLEMENTAL/FINAL (05/07/2020) UPDATE: PART A 4, 11, AND 14"

About This Pipeline Incident

Pipeline incident data is reported to the Pipeline and Hazardous Materials Safety Administration (PHMSA). All significant incidents involving fatalities, injuries, or property damage over $50,000 must be reported.

Back to All Incidents More Incidents in